Dock Wall Repair Works
Caernarfon. Phase 2
Client
WJ Developments Ltd
Contractor
Colin Jones (Rock Engineering) Ltd
Designer
Mott MacDonald
Duration
2 weeks
Key Personnel
General Manager – Richard Wyn Owen
Contracts Manager – Darren Moore
Site Foreman – Jack Jones
DESCRIPTION OF PROJECT:
Continuing with repair work to the dock wall and incorporating the staircase protection measures.
Accessing the area of the dock wall using rope access techniques, phase 2 works were mainly:
- repointing the cracks and sections of the masonry with material suitable for the marine environment, using clean, fresh water into mortar mixture.
- Repointing and thoroughly cleaning of the masonry areas
- anchor bolts placed into wall to fix material to structure
- cutting back and cleaning of voids and cracks, before repairing
- replacing displaced or missing bricks/stones
AS the area is a SAC and SSSI protected area, we were mindful of our environmental impact.