Home > Projects > Llechwedd Cheese caverns
Llechwedd Cheese caverns
Client
Llechwedd / Greaves Welsh Slate Company Limited
Contractor
Colin Jones (Rock Engineering) Limited
Designer
GWP Consultants
Duration
12 weeks
Key Personnel
General Manager – Richard Wyn Owen
Contracts Manager – Darren Moore
Site Foreman – James Oakes
DESCRIPTION OF PROJECT:
Following design in report, we carried out safeguarding work internally and externally of the cavern, using rope access techniques and the Marini, with netting and bolt installation. Work also included:
- rock drilling and bolt installation, as well as rock netting
- Vegetation clearance
- hand & machine scaling – to remove loose materials
- spot bolts and/or cable straps to secure potentially unstable blocks with bolts/dowels as appropriate.
- draped & contoured rockfall netting system, in accordance with design