Retaining walls repairs
Brighton
Client
Pilgrims Friend Society
Contractor
Colin Jones (Rock Engineering) Ltd
Designer
Daear Geo Consulting Ltd & Vale Consultancy Ltd
Duration
4 months
Key Personnel
General Manager – Richard Wyn Owen
Contracts Manager – Darren Moore
Site Foreman – Jack Jones
DESCRIPTION OF PROJECT:
We were asked to undertake repairs on an existing retaining wall. The work was in two phases
Phase 1:
First, we were tasked to test the existing anchors and then undertaking additional trial pits and core samples
Phase 2:
Then, carrying our strengthening work to the retaining wall which consisted of soil nails and vertical steel PFC along the wall that were being secured with steel bolts. Brick pillars were constructed around the steel and infilled with concrete.
Work was finished off with restoration work to the garden.