Devon
Client
Bernie Sweeney
Contractor
Colin Jones (Rock Engineering) Ltd
Duration
4 weeks
Key Personnel
General Manager – Richard Wyn Owen
Contracts Manager – Darren Moore
Site Foreman – Jack Jones / James Oakes
Description of Project
Using our 40:30 Merlo for access, work was carried out to the rockface to stabilise.
Work included:
- Scaling and removal of the rocks
- Installing erosion control matting
- Installing rock fall netting and soil nails / rock anchors
- Where required, vegetation clearance and removal.
All work was carried out following Covid 19 guidelines on social distancing.