Client

PRIVATE

Contractor

Colin Jones (Rock Engineering) Limited

Designer

Groundsolve Ltd

Duration

8 weeks

Key Personnel

General Manager – Richard Wyn Owen

Contracts Manager – Darren Moore

Site Foreman – James Oakes / Carwyn Ephraim

DESCRIPTION OF PROJECT:

In a SAC and SSSI protected area, stabilising a potentially unstable slope to the rear of a property, using soil nails and netting after de-vegetation.
Accessing area from the farmyard above and behind the property; using rope-access techniques to work on the slope and using a drilling mast to install the anchors.

  • Men woking on the slope stabilisation
  • Picture of the completed work of the slope stabilisation